I. PEKERJAAN TANAH 1. Galian Galian Pondasi Menerus : Panjang Galian = 28 M Luas Galian = 0,5 x 0,5 = 0,25 M 2 Volume Galian = 28 x 0,25 = 7,00 M 2 Galian Tapak Trasram : Panjang Galian = 10 M Luas Galian =0,15 x 0,30 = 0,045 M 2 Volume Galian = 10 x 0,045 = 0,45 M 2 Total Volume Galian Tanah = 7,00 + 0,45 = 7,45 M 2 SNI 2835:2008-6.1 Mengali 1 M3 tanah biasa sedalam 1 meter Pekerja 0,7500 x 7,45 = 5,6 HOK Mandor 0,0250 x 7,45 = 0,2 HOK 2. Urugan Urugan Pasir bawah Pondasi Tebal = 0,05 M Panjang = 28,00 M Volume = 0,05 x 0,50 x 28,00 = 0,70 M3 Urugan Pasir di bawah Lantai Tebal = 0,07 M Luas Lantai = 40,00 M2 Volume = 0,07 x 40 = 2,80 M3 Total = 3,50 SNI 2835:2008-6.11 Menguruk 1 M3 Pasir Urug Pasir Urug 1,2 x 3,50 = 4,2 M3 Pekerja 0,300 x 3,50 = 1,1 HOK Mandor 0,010 x 3,50 = 0,0 HOK Urugan Tanah dibawah lantai Tebal = 0,7 M Luas Lantai = 40 M2 Volume = 0,7 x 40 = 28,00 M3 Total Urugan Tanah = 31,50 ...